Saturday, May 17, 2014

Week 4, Day 5

Today was non-productive and a bit disappointing as we now are off the schedule by 2 days.  The carpenter came by to pick up some tools and the drywall lead dropped off some materials that will be needed for the taping and mudding of the walls.  A team is supposed to work on Saturday to do the initial taping of the walls which helps catch up the schedule some, but we know for sure now that we won't see any cabinetry before Memorial Day which was going to be exciting to look at over the 3 day weekend.  Hopefully things stay on the newly revised schedule so that cabinets can start going in the Tuesday after Memorial Day.

So looking into the next week here's the plans as we know them today:

  • Tape, mud, and smooth the wallboard
  • Prime the wallboard for painting
  • Paint the wallboard. A contractor will be doing the kitchen area and we are going to paint the living room and hallway.  I guess I know what the Mr. and I will be doing over the long weekend.
  • Finish the new siding and trim work on the outside of the house where the new window was installed.

No comments:

Post a Comment